Central Nyack Storm Drainage Improvement
August 12, 2008 - 11:11am — mmase
Project Overview:
The Town of Clarkstown needed a cost efficient design solution to address problems with both surface and subsurface drainage due to insufficient / improperly placed inlets and inadequate channel /culvert capacity. Numerous streets and adjacent lots required the improvements to alleviate street and local flooding conditions that were plaguing the neighborhood.
Service:
Site/Civil Engineering
Service:
Drainage Analysis
Service:
Site/Civil EngineeringDrainage Analysis Drainage Design
Location:
Central Nyack, New York
Client:
Town of Clarkstown, Department of Environmental Control
Project Type:
Stormwater Management
Role:
Prime
Contract Period:
2005-2006
Construction Cost:
3,000,000
Image:
25a - Central Nyack Storm Drain.jpg
Location
Central Nyack, New York
Client
Town of Clarkstown, Department of Environmental Control
Our Role
Prime
Central Nyack, New York
Client
Town of Clarkstown, Department of Environmental Control
Our Role
Prime
Project Type
Stormwater Management
Contract Period
2005-2006
Construction Cost
3,000,000
Stormwater Management
Contract Period
2005-2006
Construction Cost
3,000,000
Services
Site/Civil Engineering
Drainage Analysis
Site/Civil EngineeringDrainage Analysis Drainage Design
Site/Civil Engineering
Drainage Analysis
Site/Civil EngineeringDrainage Analysis Drainage Design